Current Planning & Design Projects
- Front Beach Road Streetscape Guidelines
Click Here
- North Thomas Road
- Prefinal Design except utilities complete
- Front Beach Road Segment 2
- Final design underway from South Thomas Road intersection through Richard Jackson Boulevard intersection.
- Expected Completion summer 2010
- SR 79 from Back Beach Road to Front Beach Road
- PD&E and Preliminary Design Reevaluation underway
- Expected completion winter 2010
- Front Beach Road PD&E
- Underway
- Expected Completion Date Fall 2010
- FBR Public Hearing Meeting Packet (3.08 MB)
Click Here
- FBR Type 2 Final Draft for Public Availability (6,403.21 KB)
Click Here
- FBR Draft PER for Public Availability (180,459.19 KB Very large file!)
Click Here
Current Construction Projects
- Front Beach Road Segment 1 and
South Thomas Drive Reconstruction
Click Here
- Began September 9, 2009
- Expected Completion Date October 2011
Completed Planning, Design & Construction Projects
- Richard Jackson Boulevard Click Here
- Began September 4, 2007
- Completed Summer 2009
- Churchwell Drive Click Here
- Began April 2, 2007
- Completed April 2008
- East Multimodal Center Site Clearing, Hydro seeding and Fencing
- Began October 2007
- Completed January 2008
- Stormwater Pond Site, 10270 Front Beach Road Clearing, Hydro seeding and Fencing
- Began January 2008
- Completed March 2008
- Churchwell Drive and Richard Jackson Boulevard Landscape Maintenance
- Transit Operational Plan
- South Thomas and Front Beach Road from South Thomas intersection east through the Middle Beach/North Thomas intersection design.
- Clara, Powell Adams, Hills and Alf Coleman Road
- Preliminary Designs Completed